Solar and Batteries for 24/7 Business Sites in Hertfordshire

Why a site that never switches off suits solar, how to size the array to your base load, the G99 route with UK Power Networks, and when a battery helps.

Solar and Batteries for 24/7 Business Sites in Hertfordshire

A site that draws power around the clock is close to the best case for solar: almost every unit the panels generate is used on the premises instead of being exported. The rule is to keep the array's peak output at or below the site's lowest demand, then let the grid application and any battery follow from that number.

That covers data centres, server rooms, cold stores and 24/7 warehouses. This guide is written for sites in Hertfordshire.

Why does a constant base load suit solar?

Base load is the demand a site never drops below: the cooling, IT and lighting that run at 3am on a Sunday as well as at noon on a Tuesday. For most businesses the case for solar turns on how much of the generation is used on site, because a unit used on the premises replaces a unit bought from the supplier, while an exported unit is paid at whatever export rate the business has agreed.

An office that empties at six and closes at weekends uses only part of what a roof array produces, and the rest is exported. A site with a flat, high base load is different. As long as the array's output stays below that floor, every kilowatt-hour it generates is consumed on site, in every season, including weekends and bank holidays. There is no occupancy pattern to predict, and the numbers do not depend on export income.

Ofgem's Smart Export Guarantee covers solar installations with a total installed capacity of up to 5 MW in Great Britain (checked on 24 Nov 2026), so a surplus can still be paid for, but a well-sized always-on site should have very little.

How big should the system be for your base load?

Start with data, not roof area. If the supply has half-hourly metering, ask the supplier for twelve months of half-hourly readings and find the lowest demand during daylight hours, season by season. Summer matters most, because that is when an array produces the most, but check both ends of the year: a cold store and a server room do not draw the same pattern in July and January.

For illustration only: a cold store that never draws less than 60 kW in daylight could take an array whose peak AC output stays under 60 kW and still use every unit on site. Push the array beyond that floor and a growing share of summer midday output has nowhere to go but the grid, a battery, or nowhere at all if export is capped.

Two numbers on a quote decide where a design sits:

  • Inverter AC capacity, in kW and in amps per phase. This is what the network operator assesses, and it sets the ceiling on what the site can send back to the grid.
  • Expected self-consumption, as a share of annual generation, calculated from your own half-hourly data rather than a generic profile.

Roof area sets the upper limit, and on a large distribution shed it may allow far more than the base load can absorb. The choice is then between a smaller array that is almost all self-consumed and a larger one with an export limit or a battery. Once the size is settled, the price follows from it, and this cost guide to solar for data centres sets out UK per-kW benchmarks by system size and by type of site.

Which grid application will a 24/7 site need?

Almost certainly G99. The Energy Networks Association's connection guidance puts the boundary at 16 A per phase, which it equates to 11.04 kW on a three-phase supply and 3.68 kW on a single-phase supply (checked on 24 Nov 2026). At or below that, EREC G98 applies; above it, EREC G99 does, and an array sized for a real base load will be above it. Our guide to G98, G99 and the SGI routes covers the thresholds in detail.

Hertfordshire falls within UK Power Networks' Eastern Power Networks area, so that is where the application goes. Under G99 the application comes first and the installation after. The ENA's guide for Type A modules (from 0.8 kW to under 1 MW, connected below 110 kV) says the network operator's connection offer should set out the works needed to connect, any works to extend or reinforce its network, the costs, and whether it will need to witness commissioning. It also notes that offers are time limited, with an acceptance period typically in the range of 30 to 90 days.

Export limitation is where an always-on site has an advantage. The same guidance describes export limiting devices, which set a level above which the system will not export, and says they may allow a constrained connection that reduces the need for reinforcement; the technical standard for these schemes is EREC G100. Where the network is constrained, it says the operator may offer a connection with restrictions such as a maximum export level. A site whose demand rarely falls below the array's output gives up very little by accepting a low export limit, although a limit does not take the project out of G99. We prepare and submit the G99 application to UK Power Networks as part of a project.

What does a battery add on a site that never switches off?

Less than on a typical business site, and that is worth knowing before anyone quotes for one. If the array is sized under the base load, there is rarely any surplus solar to store. A battery earns its place in narrower cases:

  • An array larger than the base load can absorb. The battery stores the summer midday surplus for use later in the day, instead of it being exported or curtailed under an export limit.
  • Moving grid import in time. If the site's tariff has time-of-use pricing, the battery can charge when grid electricity is cheaper and discharge when it is dearer.
  • Working within a tight connection. Paired with an export limit, storage can let a site install more generation than the network would otherwise take as export.

The ENA's guidance says network operators treat storage as demand when it imports and as generation when it exports, so a battery has to meet G98 or G99 just as the panels do. It also says that where storage is intended to run in island mode during a power outage, the fast-track route for integrated solar and storage does not apply and the standard G99 process does. For a data centre or a cold store that distinction matters: a battery bought to shift energy is not a replacement for the site's UPS or standby generation unless it has been designed, protected and applied for as backup. Decide at the start which job it is there to do.

What should a Hertfordshire business ask for in a survey?

A survey for an always-on site should answer the sizing and connection questions in writing before a price is fixed. Ask for:

  • The demand data used: twelve months of half-hourly readings, and the minimum daytime demand the design is sized against, by season.
  • The AC capacity and phase arrangement: in kW and amps per phase, with the share of generation expected to be used on site.
  • The export position: whether an EREC G100 export limit is proposed, at what level, and what it does to annual generation.
  • The G99 plan: who prepares and submits the application to UK Power Networks, and who carries any reinforcement cost named in the connection offer.
  • The battery's job, if one is proposed: energy shifting or backup, whether island mode is intended, and how that changes the application.
  • Working around operations: how the roof work and the final connection are scheduled so that cooling, IT and stock are not interrupted.
  • The business case assumptions: the import price used, any export income, and business rates. In England, plant and machinery that generates or stores power mainly or exclusively from renewables such as photovoltaics is left out of rateable value for any day before 1 April 2035, under SI 2022/405 (checked on 24 Nov 2026).

If you run a site in St Albans or elsewhere in Hertfordshire that never switches off, talk to us about a survey. Our commercial solar installers page sets out the wider commercial position.

Sources: Energy Networks Association, Distributed Generation Connection Guide: G99 Type A; Ofgem, Smart Export Guarantee: generators; The Valuation for Rating (Plant and Machinery) (England) (Amendment) Regulations 2022 (SI 2022/405). Checked on 24 Nov 2026. Confirm current requirements with UK Power Networks for a specific site.

Related Topics

solar for 24/7 business sitessolar panels for cold stores Hertfordshiresolar for server roomssizing solar to base loadG99 export limitation businesscommercial battery storage Hertfordshire

Get Your Free Solar Panel Quote

Fill in the form below for a free, no-obligation solar survey. Our Hertfordshire team will get back to you within 24 hours.

By submitting this form, you agree to our privacy policy. We never share your data.

St Albans Contact Information

  • Head Office & Showroom

    Arquen House, 4–6 Spicer St,
    St Albans, AL3 4PQ

  • Phone

    0800 470 0922

    Mon-Fri: 8am - 6pm

  • Email

    sales@sola-uk.com

Opening Hours

Monday - Friday08:00 - 18:00
Saturday09:00 - 16:00
SundayClosed