Skip to main content
Back to Blog

Solar Panel Installation UK: Steps, Costs and Timescales

Solar panel installation in the UK step by step: survey, design, G98 or G99, scaffold, fit, MCS certificate. 2025/26 costs by system size, VAT and timings.

Last reviewed by the SOLA UK team. Sources are named beside each figure.

The quick answer

  • The steps: survey and roof assessment, design with a written MCS generation estimate, the grid route (G98 notification or G99 approval), scaffold, fitting, commissioning, then your MCS certificate.
  • Time on the roof: one to two days on most homes. The grid route, not the roof, is what usually sets the start date.
  • Cost: the government's MCS-based median for 4 to 10 kW systems installed April 2025 to March 2026 was £1,546 per kW, about £7,000 for a 4.5 kW system. The Energy Saving Trust puts a typical 4.5 kWp home system at around £7,600.
  • VAT: 0% on domestic installation until 31 March 2027, then 5% from 1 April 2027.
  • Planning: most houses are permitted development under Class A. Listed homes and some flat roofs in protected areas need consent first.
  • Grid: up to 16 A per phase (3.68 kW on a single-phase supply) the installer notifies within 28 days of commissioning (G98). Above that, G99 approval comes before installation.
Solar Panel Installation UK: Steps, Costs and Timescales

What solar panel installation involves

Solar panel installation in the UK follows a set sequence, and most of it happens before anyone climbs a ladder. What happens after commissioning is a shorter list than people expect: see what solar maintenance actually involves. A certified installer assesses the roof, designs the system, gives you a written generation estimate, sorts out the grid route, puts up the scaffold, fits the panels and inverter, commissions the system and registers it with MCS. For how we scope and specify a domestic system, see residential solar. On most homes the roof work itself takes one to two days. The paperwork either side is what decides when it starts and whether you can be paid for exported power.

This guide covers each stage, what solar PV installation costs at different system sizes (using the government's own 2025/26 cost data), the VAT deadline, planning rules and how to choose an installer. It is written by SOLA UK, an MCS-certified installer based in St Albans, and every figure names its source.

Solar panel installation, step by step

1. Survey and roof assessment

The installer looks at the roof's orientation, pitch, shading and condition, the rafters and battens, the route to your consumer unit and your meter and supply arrangement. MIS 3002, the MCS Solar PV Standard, requires the building to be assessed by a competent professional to confirm it is suitable and that the work will not compromise its compliance with the Building Regulations. If the site is evaluated remotely rather than visited, the generation estimate must say so.

2. Design and a written quote

Before you sign, MIS 3002 requires a generation estimate calculated by the standard MCS method, plus a self-consumption estimate for your household. The estimate shows the installed capacity in kWp, the orientation, the pitch, the shade factor and the expected annual output, so quotes from different companies can be compared line by line. Our checklist of what a solar quote must contain covers the rest.

3. The grid route: G98 or G99

Every system connected to the network has to be reported to the Distribution Network Operator (DNO), and the route depends on current, not on panel count. EREC G98 covers installations up to and including 16 A per phase. The Energy Networks Association (ENA) puts that at 3.68 kW on a single-phase supply and 11.04 kW on three-phase, counting everything installed at the property. MIS 3002 measures it as the total AC output of all generators, so the inverter rating is what counts: a larger array on a 3.68 kW inverter can still be a G98 job. On the G98 route the installer notifies the DNO within 28 days of commissioning. Above the threshold, EREC G99 applies and approval has to be granted before installation, which is the step most likely to move a start date.

Batteries count towards the total. MIS 3002 gives the example of a 3 kW solar system plus a 3 kW battery on the same single-phase supply: together they exceed 16 A, so the job becomes a G99 application.

4. Scaffold

Safe access goes up first, usually a day or two before the fitting team arrives, and comes down once the array is finished and checked.

5. Fitting the system

The team fixes the mounting rails or in-roof tray, lays the panels, runs the DC cabling to the inverter, installs isolators and connects the AC side to your consumer unit. Bird mesh goes in at the same time where it is wanted. On a typical home this is the one-to-two-day part.

6. Commissioning and testing

The system is inspected and tested against the IET Code of Practice for Grid Connected Solar Photovoltaic Systems, and the test results go into your handover pack. The installer then completes the G98 notification, or confirms the G99 connection.

7. Handover and the MCS certificate

You should receive a document pack, collated and explained to you: the system design, datasheets, test results, warranties and operating instructions. The installer registers the system on the MCS Installation Database no later than 10 working days after commissioning, and your MCS certificate follows. Our MCS handover pack checklist lists every document. With the certificate you can apply for a Smart Export Guarantee tariff with any supplier you choose.

How long solar panel installation takes

Timings for a domestic installation. Sources: ENA guidance on G98/G99; MIS 3002; Octopus Energy on export MPANs. Last updated October 2026.
StageTypical timeWhat sets it
Survey and designOne visit, then the written quoteRoof access and your usage data
G98 notificationFiled within 28 days after commissioningNo wait before installation
G99 applicationApproval needed before installation; can add weeksThe DNO's assessment of the local network
Roof workOne to two days on most homesRoof size, number of slopes, battery
MCS certificateWithin 10 working days of commissioningInstaller registration on the MCS database
Export MPAN for SEGThe longest part of an export application, per OctopusThe DNO, outside the supplier's control

Solar panel installation cost in the UK

The most reliable public cost figures come from the Department for Energy Security and Net Zero (DESNZ). Its Solar PV cost data, published on 28 May 2026, is built from installations registered with MCS between April 2025 and March 2026. On its total installed capacity basis, the median cost was £1,595 per kW for systems up to 4 kW and £1,546 per kW for systems from 4 to 10 kW. DESNZ's figures include VAT where it applied and exclude batteries. The table multiplies those medians by common system sizes, so treat each figure as a national midpoint rather than a price for your roof.

Indicative domestic solar panel installation costs. Last updated October 2026. Sources: DESNZ Solar PV cost data 2025/26 (TIC basis, published 28 May 2026, gov.uk/government/statistics/solar-pv-cost-data), median cost per kW multiplied by system size; Energy Saving Trust solar panels advice page (last updated 1 October 2026). Not a quote.
System sizeIndicative installed costBasisWhat's included
3 kWAbout £4,800DESNZ median, up to 4 kW: £1,595 per kWPanels, inverter, mounting, fitting, MCS registration; no battery
4.5 kWp (typical home, around 12 panels)Around £7,600 (EST); about £7,000 (DESNZ)Energy Saving Trust benchmark; DESNZ median, 4 to 10 kW: £1,546 per kWPanels, inverter, mounting, fitting, MCS registration; no battery
6 kWAbout £9,300DESNZ median, 4 to 10 kWAs above; G99 on single phase unless inverter output is held to 3.68 kW
8 kWAbout £12,400DESNZ median, 4 to 10 kWAs above; same G98/G99 rule as 6 kW
10 kWAbout £15,500DESNZ median, 4 to 10 kWAs above; can stay within G98 on a three-phase supply (11.04 kW)
Battery storage, addedAround £5,000 to £8,000Energy Saving TrustBattery and its installation; counts towards the G98 limit

Two notes on reading it. DESNZ also publishes the same data on a declared net capacity basis, where the medians are higher (£1,780 per kW up to 4 kW and £1,697 per kW for 4 to 10 kW), because that measure records a smaller capacity for the same system. And the real price of your job turns on scaffold and access, tile type, how many roof slopes the array uses, the cable run, the inverter and whether a battery is included. A written quote should show each of those. For a fuller breakdown see our solar panel costs guide, and for battery options see battery storage.

The Energy Saving Trust states that there are no dedicated government grants for solar panels in the UK at the moment. The exception is the Warm Homes: Local Grant, which councils use to fit solar panels in qualifying lower-income homes with an EPC rating of D to G, as our Warm Homes Grant guide explains. Any other "solar grant" offer is describing something else.

VAT on solar panel installation

In Great Britain, HMRC's VAT Notice 708/6 zero-rates the installation of energy-saving materials, including solar panels, in residential accommodation from 1 April 2022 to 31 March 2027. From 1 April 2027 the rate reverts to the reduced 5%, not to 20%. The zero rate covers labour as well as equipment, and batteries installed in homes have qualified since 1 February 2024. Commercial installations are charged standard-rate VAT at 20%, which a VAT-registered business can normally reclaim; see commercial solar for how business installations are priced and taxed.

Planning permission for solar panels

Most domestic solar panel installation needs no planning application. Panels on a house are permitted development under Class A of Part 14, Schedule 2 of the General Permitted Development Order, as amended by S.I. 2026/896 from 27 August 2026. On a pitched roof they must protrude no more than 0.2 metres beyond the roof slope and sit no higher than the highest part of the roof, excluding chimneys. On a flat roof the limit is 0.6 metres above the highest part of the roof.

The exceptions to check:

  • Conservation areas: the Class A restriction covers equipment on a wall, balcony or roof enclosure that fronts a highway. It does not remove permitted development rights from roof slopes.
  • Flat roofs on protected land (conservation areas, National Parks, the Broads, National Landscapes and World Heritage Sites): apply to the council for a prior approval decision before work starts.
  • Listed homes: since 27 August 2026 a listed house sits outside Class A altogether, so planning permission and listed building consent are both needed.
  • Article 4 Directions: a direction only removes the rights it names, so check whether one on your street mentions solar.

Non-domestic buildings fall under a separate class (Class J), which is covered on our commercial page.

Solar PV installation or solar panel installation?

They are the same job. Solar PV stands for photovoltaic: panels that turn daylight into electricity, which is what nearly everyone means by solar panel installation. Solar thermal panels heat hot water instead and are installed under a different MCS standard, MIS 3001. MIS 3002 covers solar PV installation on homes and smaller commercial roofs up to 50 kWp DC.

Residential solar panel installation is covered in detail on our residential solar page. Larger business roofs follow the same standard up to 50 kWp, then the G99 process and different tax rules apply; see commercial solar installation.

Choosing an MCS installer

MCS certification is not a legal requirement for fitting panels, but without an MCS certificate (or an equivalent recognised scheme) you will struggle to claim a Smart Export Guarantee tariff. Four checks take a few minutes each:

  • Search the MCS register for the exact company name on the quote, and check that it covers solar PV and, if you want one, battery storage (MIS 3012).
  • Check the consumer code. MCS requires certified installers to belong to a consumer code such as RECC, so the names on both registers should match.
  • Get three quotes. The Energy Saving Trust recommends quotes from at least three installers, and asking each what electricity price they used to estimate savings.
  • Limit the deposit. RECC advises consumers not to pay more than 25% of the final contract price as a deposit.

Our page on MCS certified solar installers explains what each register does and does not prove, and our guide to whether you need an MCS certificate covers what the certificate shows and how to replace a lost one. If your home is in Devon, outside the area we cover, LuminAsset is an independent consultancy that sizes the roof from aerial imagery, prices the system with and without a battery, and introduces one installer that has passed its checks, MCS certification among them.

Get a solar panel installation quote

SOLA UK installs solar panels, batteries and EV chargers across Hertfordshire, North London and the surrounding area from Arquen House, 4-6 Spicer Street, St Albans. If you are local, our solar panel installation in Hertfordshire and North London page covers the local network operator and council rules (in the capital, see solar panels London), or call 0800 470 0922. Use the form below for a written quote with the MCS generation estimate, the grid route and the VAT position on it.

Get Your Free Solar Panel Quote

Fill in the form below for a free, no-obligation solar survey. Our Hertfordshire team will get back to you within 24 hours.

By submitting this form, you agree to our privacy policy. We never share your data.

St Albans Contact Information

  • Head Office & Showroom

    Arquen House, 4–6 Spicer St,
    St Albans, AL3 4PQ

  • Phone

    0800 470 0922

    Mon-Fri: 8am - 6pm

  • Email

    sales@sola-uk.com

Opening Hours

Monday - Friday08:00 - 18:00
Saturday09:00 - 16:00
SundayClosed

What you should have at the end

When the job is finished you should hold the MCS certificate, the G98 notification or G99 confirmation, test results, datasheets and warranty documents for the panels, inverter and any battery, written workmanship terms, and access to the monitoring app. Keep them together: you will need them for the Smart Export Guarantee, a house sale, or adding a battery later. Compare export rates on our SEG calculator.

Commercial roofs are priced differently, per kWp installed, with the rate falling as systems get larger; the 2026 benchmark for commercial solar cost per kWp is checked against government installed-cost data.

Solar panel installation FAQs

How long does a solar panel installation take?

The roof work takes one to two days on most homes once the scaffold is up. The full process takes longer, and the grid route is the variable: a G98 job is notified within 28 days after commissioning, while a G99 job needs network operator approval before installation can start.

How much does solar panel installation cost in the UK?

The government's Solar PV cost data for 2025/26 puts the median installed cost at £1,595 per kW for systems up to 4 kW and £1,546 per kW for 4 to 10 kW systems, which is about £7,000 for a 4.5 kW array. The Energy Saving Trust gives around £7,600 for a typical 4.5 kWp system and around £5,000 to £8,000 for battery storage.

Do I need planning permission to install solar panels?

Usually not. Panels on a house are permitted development under Class A of Part 14 of the General Permitted Development Order if they protrude no more than 0.2 metres from the roof slope and sit no higher than the highest part of the roof, excluding chimneys. Listed homes, flat roofs on protected land and streets covered by an Article 4 Direction are the exceptions to check.

Is there VAT on solar panel installation?

Not until 31 March 2027. HMRC VAT Notice 708/6 zero-rates the installation of solar panels in residential accommodation, labour included, until then, and the rate moves to the reduced 5% from 1 April 2027. Commercial installations pay standard-rate VAT at 20%, which a VAT-registered business can normally reclaim.

What is the difference between solar PV installation and solar panel installation?

For most people there is none. Solar PV (photovoltaic) panels generate electricity, and that is what almost everyone means by solar panel installation. Solar thermal panels heat water instead, and they are installed under a different MCS standard, MIS 3001, rather than MIS 3002.

Do I need G98 or G99 approval for solar panels?

It depends on current, not kilowatts. G98 covers installations up to and including 16 A per phase, which is 3.68 kW on a single-phase supply and 11.04 kW on three-phase, and the installer notifies the network operator within 28 days of commissioning. Above that threshold, including many solar plus battery systems, G99 approval is needed before installation.

When will I receive my MCS certificate?

Within 10 working days of commissioning. The installer must register the system on the MCS Installation Database within that time, and the certificate is then sent to you. You need it to apply for a Smart Export Guarantee tariff.